Bangladesh’s Rooppur nuclear plant feeds the grid for the first time

The first unit began a trial supply of 350MW at 3:16pm on Tuesday, and the science minister said Bangladesh had become the 33rd country to generate nuclear power.

Join the conversation
Drilling rigs and excavators at the Rooppur nuclear power plant construction site in Bangladesh
Construction work at the Rooppur nuclear power plant site in Bangladesh in October 2018. File photo. — Laura Gil/IAEA
Listen to this articleBangladesh’s Rooppur nuclear plant feeds the grid for the first time3 min · device voice0:00 / 2:38

— Bangladesh’s first nuclear power plant fed electricity into the national grid for the first time on Tuesday, as the first unit at Rooppur began a trial supply of 350 megawatts.

The supply began at 3:16pm, the Bangladesh Atomic Energy Commission said in a press release. Science and Technology Minister Faqir Mahbub Anam, who was at the site, told reporters that Bangladesh had become the 33rd country in the world to generate nuclear power.

What happens next

The initial connection is scheduled to last about eight to 10 hours, during which engineers will monitor the unit’s turbine, generator and the systems that synchronise it with the grid, the release said. The unit will then be disconnected for further tests and reconnected after about 28 hours for another four to six hours.

The release stressed that the connection does not mean the plant has entered commercial operation. The reactor and its equipment will go through months of testing, the unit may be shut down temporarily at different stages, and the plant cannot guarantee an uninterrupted baseload supply while testing continues. Power generated during this period will go to consumers, and the Power Grid Company of Bangladesh will take steps to keep the grid stable as the plant’s output fluctuates.

Under the agreement with the Russian contractor, the first unit will undergo a 10-month trial operation before it begins commercial generation at full capacity, according to the release. Once the initial tests are completed successfully, the plant will need approval from the Bangladesh Atomic Energy Regulatory Authority to move to the next stage of trial operation.

About Rooppur

The plant, about 160 kilometres from Dhaka, is being built with Russian financial and technical assistance under a 2015 agreement. It has two units of 1,200MW each, giving a combined capacity of 2,400MW. The first shipment of nuclear fuel arrived in 2023, but progress slowed amid political instability and wider global conditions, reports said.

TT Foreign Desk

World news from The Thursday Times' foreign desk.

More from this desk

The conversation

Comments are open on this story. An editor reads every one before it appears.

No one has said anything yet. Be the first.

Published by Thursday Media International thursday.media