DAMASCUS (The Thursday Times) — Syria signed an agreement with a Czech company on Sunday to rehabilitate three generating units at the Aleppo Thermal Power Plant, a project that will restore 639 megawatts of capacity once it is finished, officials said.
The Syrian Electricity Company and Energy Care signed the deal at the Energy Ministry in Damascus. Energy Minister Mohammad al-Bashir and the Czech ambassador to Syria, Vitezslav Pivonka, attended. Imad Abu Ali, the plant director, signed for the Syrian side, and Haitham Eid, the company’s representative in Syria, signed for Energy Care.
The agreement covers the plant’s second, third, and fourth units, each with a design capacity of 213 megawatts. Under the timetable, the third unit is due back in service 18 months after work begins, the fourth after 24 months, and the second after 30 months.
A bigger plant on the grid
When all three units are running, the plant’s total design capacity is expected to reach about 1,040 megawatts. That figure includes roughly 400 megawatts from the first and fifth units, which have already been repaired.
Abu Ali said in May that repairs to those two units had lifted output to about 400 megawatts and made supplies more reliable. The fifth unit was then generating 202 megawatts and the first about 195 megawatts. The work addressed faults in the plant’s main and auxiliary systems, including air preheaters, forced-draft air systems, and water treatment equipment.
The plant, in the eastern countryside of Aleppo, is a major source of electricity for northern Syria and feeds the national grid. Officials describe the project as part of wider Energy Ministry efforts to rehabilitate power stations, restore generating capacity, and improve the reliability of the grid as Syria works to meet growing demand.